Borehole Pump Installation Procedures and Technical Requirements

A step-by-step borehole pump installation procedure: pre-installation checks, assembly, cable splicing and testing, lowering, setting depth, wellhead, electrical connection and commissioning.

By Quantum Geoconsultants pump installation teamUpdated 19 November 20262 min read
TopsoilLava flowOlder lavas & tuffsStatic water level (pump off) Pumping water level ◀ Submersible pump & motor ◀ Screen below the pump Pump sized from test pumping

⚙️ Borehole Pumps & Solar: a technical article by the Quantum Geoconsultants pump installation team.

A correctly selected pump can still fail early if installed poorly. This article sets out a practical borehole pump installation procedure and the technical requirements for a reliable result.

1. Pre-installation checks

2. Assemble on the surface

  1. Couple the pump end to the motor if supplied separately.
  2. Fit the non-return valve at the pump outlet if not built in.
  3. Connect the first length of rising main.
  4. Attach the safety rope to the pump’s lifting eyes.

3. Cable splicing

The motor lead is joined to the drop cable using a waterproof splice kit (heat-shrink or resin). The splice is the most common failure point, so it must be made carefully and allowed to cure.

4. Insulation and continuity tests

Test cable and motor insulation resistance with an insulation tester, and continuity of each conductor, before lowering. Record the values for future comparison.

5. Lowering the pump

6. Setting depth

Set the pump below the lowest expected dynamic water level with margin, usually above the screens, and not too close to the bottom where sediment collects. If set below screens, use a cooling shroud. See pump submergence.

7. Dip tube

Install a small-diameter dip tube alongside the rising main so water levels can be measured safely in future.

8. Wellhead

9. Electrical connection

Connect to the control panel or solar controller with correct protection: overload, dry-run, voltage and phase protection, and earthing and surge protection. See control panels and protection.

10. Commissioning

Start the pump, check rotation (three-phase), measure flow, pressure, current and voltage, and monitor the water level. Compare results with the pump curve. See pump testing after installation.

11. Handover

Provide the owner with a record of the pump model, setting depth, cable size, test results and maintenance advice.

How Quantum Geoconsultants can help

Our technicians install pumps to these standards. See borehole pump installation in Kenya and rising mains, cables and accessories.

Frequently asked questions

Why test cable insulation before installation?

An insulation resistance test detects damaged cable or a faulty splice before the pump is lowered, avoiding having to pull it out again.

Why use a safety rope?

It supports the pump if the rising main fails and allows the pump to be recovered safely. Stainless steel or suitable non-rotting rope is used.

How deep should the pump be set?

Below the lowest expected dynamic water level with a safety margin, usually above the screens, as determined from test pumping.

⚙️ Borehole pump size calculator

Enter your borehole's numbers from the test pumping report (or your best estimate) to see the total head, the flow and roughly how big a submersible pump or solar array you need.

0total head (m)
0pump flow (m³/hour)
0solar array (watts)

Rough planning figures only. Total head = pumping water level + tank height + an allowance for pipe friction. The final pump is chosen from the manufacturer's pump curves, your test pumping yield and your water quality.

Get a borehole pump installation quote