A correctly selected pump can still fail early if installed poorly. This article sets out a practical borehole pump installation procedure and the technical requirements for a reliable result.
1. Pre-installation checks
- Review the test pumping report and agreed pump setting depth.
- Check borehole depth and casing condition, ideally with a camera inspection for older boreholes.
- Confirm the pump, motor, cable, rising main and accessories match the design.
- Check the power supply voltage and phases.
2. Assemble on the surface
- Couple the pump end to the motor if supplied separately.
- Fit the non-return valve at the pump outlet if not built in.
- Connect the first length of rising main.
- Attach the safety rope to the pump’s lifting eyes.
3. Cable splicing
The motor lead is joined to the drop cable using a waterproof splice kit (heat-shrink or resin). The splice is the most common failure point, so it must be made carefully and allowed to cure.
4. Insulation and continuity tests
Test cable and motor insulation resistance with an insulation tester, and continuity of each conductor, before lowering. Record the values for future comparison.
5. Lowering the pump
- Use a tripod, winch or lifting equipment with a pipe clamp.
- Add rising main lengths with correct joints and torque.
- Tape or clip the cable and rope to the rising main at regular intervals.
- Fit a torque arrestor on larger pumps to centralise them and prevent twisting.
- Lower slowly, avoiding damage to cable against the casing.
6. Setting depth
Set the pump below the lowest expected dynamic water level with margin, usually above the screens, and not too close to the bottom where sediment collects. If set below screens, use a cooling shroud. See pump submergence.
7. Dip tube
Install a small-diameter dip tube alongside the rising main so water levels can be measured safely in future.
8. Wellhead
- Seal the borehole top with a proper wellhead plate or cap.
- Fit a non-return valve, gate valve, pressure gauge, sampling tap and flow meter.
- Protect the wellhead from surface water and tampering.
9. Electrical connection
Connect to the control panel or solar controller with correct protection: overload, dry-run, voltage and phase protection, and earthing and surge protection. See control panels and protection.
10. Commissioning
Start the pump, check rotation (three-phase), measure flow, pressure, current and voltage, and monitor the water level. Compare results with the pump curve. See pump testing after installation.
11. Handover
Provide the owner with a record of the pump model, setting depth, cable size, test results and maintenance advice.
How Quantum Geoconsultants can help
Our technicians install pumps to these standards. See borehole pump installation in Kenya and rising mains, cables and accessories.
Frequently asked questions
Why test cable insulation before installation?
An insulation resistance test detects damaged cable or a faulty splice before the pump is lowered, avoiding having to pull it out again.
Why use a safety rope?
It supports the pump if the rising main fails and allows the pump to be recovered safely. Stainless steel or suitable non-rotting rope is used.
How deep should the pump be set?
Below the lowest expected dynamic water level with a safety margin, usually above the screens, as determined from test pumping.
⚙️ Borehole pump size calculator
Enter your borehole's numbers from the test pumping report (or your best estimate) to see the total head, the flow and roughly how big a submersible pump or solar array you need.
Rough planning figures only. Total head = pumping water level + tank height + an allowance for pipe friction. The final pump is chosen from the manufacturer's pump curves, your test pumping yield and your water quality.
Send these numbers on WhatsAppGet a borehole pump installation quote
Send us your test pumping report, borehole depth and where the tank will sit. We will size the right submersible or solar pump and send a quotation for supply, installation and commissioning.