Installing a pump is not the end of the job. Pump testing and commissioning confirm that the system performs as designed and set a baseline for future maintenance. This article explains what to measure and why.
Before starting
- Record insulation resistance and continuity of cable and motor.
- Check all valves are in the correct position.
- Measure static water level through the dip tube.
- Confirm control and protection settings.
Start-up checks
- Rotation: for three-phase pumps, wrong rotation still pumps but with much lower output. Check by comparing output with phases swapped if in doubt.
- Noise and vibration at the wellhead.
- Water clarity: initial turbidity should clear.
Measurements
| Parameter | How | Why |
|---|---|---|
| Flow | Flow meter or timed volume | Confirms output |
| Delivery pressure | Gauge at wellhead | Gives head at the surface |
| Dynamic water level | Dip meter | Confirms submergence and drawdown |
| Current per phase | Clamp meter | Compares load with motor rating |
| Voltage | Meter at panel and, if possible, under load | Checks supply and voltage drop |
Comparing with the pump curve
Calculate total head from dynamic water level, delivery pressure and height of the gauge. Plot the measured flow and head on the pump curve. A point well below the curve suggests problems such as wrong rotation, worn parts, leaks in the rising main or a mismatched model. See TDH and flow rate.
Electrical checks
- Current should be within the motor’s rated current and balanced between phases.
- Voltage should be within the motor’s tolerance under load.
- Protection devices should trip at the correct settings.
See control panels and protection.
Solar systems
For solar pumps, record flow and controller readings (power, voltage, frequency or speed) at different times of day, and total daily volume over several days. Compare with design predictions. See solar controllers.
Protection tests
- Simulate low water to confirm dry-run protection works.
- Test tank float switches.
- Confirm restart delays work.
Recording the baseline
A commissioning sheet records all measurements, pump details, setting depth and cable data. Repeat measurements during maintenance reveal trends such as falling flow or rising current. See pump maintenance.
How Quantum Geoconsultants can help
We commission every pump we install and provide records for future servicing. See pump installation and installation procedures.
Frequently asked questions
What should be measured when commissioning a pump?
Flow, delivery pressure, water level, motor current on each phase, supply voltage and insulation resistance.
Why record baseline values?
Baseline readings let you detect wear, clogging or electrical problems later by comparing new readings with the originals.
What if the pump delivers less than expected?
Check head, valves, leaks, water level, rotation direction on three-phase pumps and whether the correct model was installed.
⚙️ Borehole pump size calculator
Enter your borehole's numbers from the test pumping report (or your best estimate) to see the total head, the flow and roughly how big a submersible pump or solar array you need.
Rough planning figures only. Total head = pumping water level + tank height + an allowance for pipe friction. The final pump is chosen from the manufacturer's pump curves, your test pumping yield and your water quality.