Warehouses, logistics hubs and factories look simple: a steel frame, a roof and a large concrete floor. But the floor slab is often the most demanding element. It carries racking legs, forklifts, trucks and stacked goods, and must stay flat for operations. A good ground investigation for warehouses protects that slab and the column foundations. This article explains what it should cover.
Loads to consider
- Column loads from the portal frame, including wind uplift.
- Rack leg point loads, often high and concentrated.
- Uniformly distributed loads from block-stacked goods.
- Vehicle loads from forklifts, reach trucks and lorries.
- Mezzanine floors and heavy machinery.
Share these loads with the geotechnical engineer when planning the investigation.
Investigation scope
- Desk study and walkover for fill, old structures, drainage and slopes.
- Topographic survey for platform levels and earthworks.
- Trial pits across the footprint for shallow soil and fill conditions. See trial pits vs boreholes.
- Boreholes at column grid locations and deeper where soft soils are possible. See how many boreholes.
- DCP or CPT for continuous strength profiles.
- Plate load tests for subgrade stiffness.
- Laboratory tests: classification, plasticity, compaction, CBR, swell and chemistry.
- Groundwater observations.
Floor slab design inputs
Modulus of subgrade reaction
Slab design uses the modulus of subgrade reaction (k), often from plate load tests or correlations with CBR. Higher k means the ground deflects less under load.
Subgrade uniformity
Variations in subgrade stiffness cause differential movement and cracking. The investigation should identify soft spots, fill pockets and changes in soil type.
Sub-base and capping
A granular sub-base, sometimes with a capping layer, provides a uniform working platform and spreads loads. Its thickness depends on the subgrade.
Long-term settlement
Large uniform loads from block stacking can consolidate soft clays below, causing long-term settlement. See foundation settlement.
Column foundations
Pad footings are common on good ground. On soft or variable ground, piles may be needed. Differential settlement between columns and the slab must be considered, as it affects cladding, doors and racking alignment. See raft vs strip vs pad.
Problem soils
Expansive clays
Black cotton soil under slabs causes heave and cracking. Typical solutions: removal and replacement with granular fill, lime stabilisation, or a suspended slab. See black cotton soil and soil stabilisation.
Uncontrolled fill
Old fill or dumped material settles unpredictably. It should be removed, or improved and tested.
Soft ground
Low-lying sites near rivers or swamps may need preloading, ground improvement or piled slabs. See soft clay.
Collapsible and saline soils
In arid areas, wetting can collapse soils and salts can attack concrete. See collapsible soils.
Platforms and earthworks
Many warehouse sites need cut-and-fill to create a level platform. The fill must be engineered:
- Suitable material from tested sources. See borrow pits.
- Placed in thin layers at controlled moisture.
- Compacted and tested with field density tests against Proctor MDD.
- Plate load tests to confirm stiffness.
Deep fill over soft ground needs settlement assessment and time to settle before slab construction.
Drainage
Water under slabs softens subgrades and activates expansive clays. Provide surface drainage away from the building, subsurface drains where groundwater is high, and a well-drained sub-base.
How Quantum Geoconsultants can help
We investigate warehouse and industrial sites with boreholes, trial pits, plate tests and laboratory testing, and provide slab and foundation design parameters. See our geotechnical surveys in Kenya and Somalia.
Frequently asked questions
Why do warehouses need a ground investigation?
Warehouses carry heavy rack and vehicle loads on large floor slabs. Weak, variable or expansive ground causes cracking, uneven floors and racking problems that are very costly to fix once operations start.
What is modulus of subgrade reaction?
A measure of how stiff the ground is under a slab, expressed as pressure per unit deflection. It is used in slab design and often derived from plate load tests or correlations.
Can a warehouse be built on fill?
Yes, if the fill is engineered: suitable material placed and compacted in layers with testing. Uncontrolled fill is a major cause of floor slab settlement.
🏗️ Request a geotechnical survey quote
The scope and cost of a geotechnical investigation depend on the size and type of structure, the site area and the ground conditions. Tell us about your project and we will propose an investigation programme and quotation.
Under the National Building Code 2024, soil testing is now expected before construction. We reply with a proposed programme and quotation.