Every foundation settles. When a building is placed on the ground, the soil compresses under the added load. A few millimetres of uniform settlement is usually harmless. Large or uneven settlement is not: it cracks walls, jams doors, breaks pipes and can make buildings unsafe. This article explains the causes of foundation settlement, the limits engineers work to and how settlement is monitored.
Types of settlement
| Type | Description | Typical soils |
|---|---|---|
| Immediate | Occurs as load is applied, mostly elastic compression | Sands, gravels, stiff soils |
| Consolidation | Slow compression as water drains from clay | Soft to firm clays and silts |
| Secondary (creep) | Continues slowly after consolidation | Soft, organic clays and peat |
See the oedometer test for how consolidation settlement is predicted.
Causes of excessive settlement
- Compressible soils: soft clay, peat or loose fill under the foundations. See foundations on soft clay.
- Variable ground: part of a building on rock and part on soil or fill.
- Poorly compacted fill under floors or foundations. See field density testing.
- Expansive clays shrinking in dry seasons. See black cotton soil.
- Collapsible soils wetted by leaks or rain. See collapsible soils.
- Groundwater lowering from dewatering or pumping, which increases effective stress.
- Erosion or washout from leaking pipes or drains.
- Cavities in limestone or coral. See cavity detection.
- Nearby excavation or new heavy buildings.
- Undersized foundations for the loads.
Total and differential settlement
Total settlement is the downward movement of a point. Differential settlement is the difference between two points. A building that settles 40 mm uniformly may show little damage; one that settles 40 mm at one corner and 10 mm at another may crack badly.
Engineers also use angular distortion: differential settlement divided by the distance between points. Limits on angular distortion relate directly to cracking risk.
Typical tolerable limits
Limits depend on the structure type, materials and use. Published guidance, including Eurocode 7 informative values and classic research by Skempton, Burland and others, suggests approximate ranges such as:
| Criterion | Indicative value |
|---|---|
| Total settlement, isolated footings on clay | Often limited to around 25 to 50 mm |
| Total settlement, rafts | Larger values may be acceptable if uniform |
| Angular distortion, onset of cracking in framed buildings | Around 1/500 is often used as a limit |
| Angular distortion, structural damage likely | Around 1/150 to 1/300 |
These are general guides. Sensitive structures, such as tanks, machinery bases and buildings with brittle finishes, need tighter limits set by the structural engineer.
Predicting settlement
A geotechnical investigation provides the data:
- Soil profile and layer thicknesses from boreholes. See borehole depth.
- Stiffness from SPT, CPT, plate tests or MASW for sands and stiff soils.
- Compressibility and consolidation rate from oedometer tests for clays.
- Groundwater levels.
The engineer calculates stress increases beneath each foundation and the resulting compression of each layer, then compares predicted settlements with the limits.
Reducing settlement
- Increase foundation size or depth.
- Use a raft to spread load and reduce differential movement. See raft vs strip vs pad.
- Improve the ground or preload it.
- Use piles to carry load to firmer strata.
- Remove and replace weak soils or poor fill.
- Provide movement joints between parts of a building with different foundations or loads.
Monitoring settlement
- Install settlement points (studs or bolts) on columns, walls or foundations.
- Establish a stable benchmark outside the zone of influence.
- Take a baseline reading before significant loading.
- Level the points at regular intervals during and after construction using precise levelling.
- Plot settlement against time and load, and compare with predictions.
For larger projects, automatic sensors, tiltmeters and crack gauges add detail. See deformation monitoring surveys.
How Quantum Geoconsultants can help
We investigate ground conditions, predict settlement and provide monitoring surveys for buildings, tanks and embankments. See our geotechnical surveys in Kenya and our guide to cracks in walls.
Frequently asked questions
Is some foundation settlement normal?
Yes. Almost all foundations settle a little as the ground compresses under load. The concern is settlement that is large, uneven or continuing, because that causes cracking and damage.
What is differential settlement?
The difference in settlement between two parts of a structure. It distorts the building and causes cracks, so it is usually more damaging than uniform total settlement.
How is settlement monitored?
By precise levelling of fixed points on the structure at intervals, sometimes with automatic sensors, compared with a stable benchmark away from the building.
🏗️ Request a geotechnical survey quote
The scope and cost of a geotechnical investigation depend on the size and type of structure, the site area and the ground conditions. Tell us about your project and we will propose an investigation programme and quotation.
Under the National Building Code 2024, soil testing is now expected before construction. We reply with a proposed programme and quotation.