Weak or problematic ground does not always mean piles. Across large sites such as warehouses, port yards, tank farms, embankments and reclamation, it is often cheaper to improve the ground itself. Modern ground improvement techniques can densify loose sands, reinforce soft clays, speed up settlement or fill voids. This article introduces the main methods and when they are used.
Why improve ground?
- Increase bearing capacity.
- Reduce total and differential settlement.
- Reduce liquefaction risk in loose saturated sands.
- Speed up consolidation of soft clays.
- Fill voids and cavities.
- Reduce permeability or stabilise excavations.
Main techniques
Surface compaction
Heavy rollers, vibratory plates and impact rollers compact the upper layers of fill and granular soils. Effective to limited depths. Controlled by field density testing. See field density tests.
Dynamic compaction
A heavy weight is dropped repeatedly from a crane onto the ground surface in a grid pattern. The impact densifies loose granular soils, fills and some collapsible soils to depths of several metres or more, depending on weight and drop height. It causes vibration and noise, so it suits open sites away from sensitive structures.
Vibro-compaction
A vibrating probe is inserted into loose sand and withdrawn in stages, rearranging grains into a denser state. Best suited to clean sands with low fines content.
Stone columns (vibro-replacement)
The probe forms holes into which crushed stone is fed and compacted, creating columns that reinforce the soil and act as vertical drains. Used in silty sands and soft to firm clays under embankments, tanks and slabs.
Preloading and vertical drains
Temporary surcharge fill causes soft clays to consolidate before construction; prefabricated vertical drains shorten drainage paths and speed it up. See foundations on soft clay and consolidation testing.
Grouting
- Permeation grouting: low-viscosity grout fills pores in sands and gravels.
- Compaction grouting: stiff grout displaces and densifies loose soil.
- Fissure and cavity grouting: fills voids in rock, karst and coral limestone. See cavity detection.
- Jet grouting: high-pressure jets mix soil with cement grout to form columns or panels.
Deep soil mixing
Augers mix cement or lime into soft soils in place, creating columns or blocks of stronger material. Used for soft clays under embankments and for excavation support.
Lime and cement stabilisation
Shallow mixing of binders into soils for roads, platforms and slabs. See soil stabilisation with lime and cement.
Removal and replacement
Excavating weak soil and replacing it with engineered fill remains a simple, effective option where weak layers are shallow.
Choosing a method
| Ground | Common methods |
|---|---|
| Loose clean sands | Vibro-compaction, dynamic compaction |
| Loose silty sands | Stone columns, dynamic compaction, compaction grouting |
| Soft clays | Preloading with drains, stone columns, deep soil mixing |
| Variable fill | Dynamic compaction, removal and replacement |
| Collapsible soils | Pre-wetting and compaction, dynamic compaction. See collapsible soils |
| Cavernous limestone or coral | Cavity grouting |
| Expansive clays | Lime stabilisation, removal and replacement |
Investigation for ground improvement
- Detailed boreholes and CPT to map weak layers and their thickness.
- Grading and fines content, critical for vibro methods. See particle size distribution.
- Groundwater levels.
- Consolidation and strength tests for clays.
- Assessment of nearby structures sensitive to vibration.
Verification
- Before-and-after CPT or SPT profiles.
- Plate load tests or zone load tests.
- Settlement monitoring. See deformation monitoring.
- Records of energy, depth and materials used at each treatment point.
How Quantum Geoconsultants can help
We investigate sites to assess whether ground improvement is suitable, and provide the data needed for design and verification testing. See our geotechnical surveys in Kenya and Somalia.
Frequently asked questions
What is ground improvement?
Treating weak or problematic ground to increase its strength, reduce compressibility or control groundwater, so that structures can be built on it without deep foundations.
Is ground improvement cheaper than piling?
Often, for large areas with moderate loads such as warehouses, tanks, embankments and yards. For heavy, concentrated loads or very deep soft ground, piles may be more economical.
How do you check ground improvement worked?
By testing before and after treatment, for example with CPT, SPT, plate load tests, settlement monitoring and zone load tests, compared with design targets.
🏗️ Request a geotechnical survey quote
The scope and cost of a geotechnical investigation depend on the size and type of structure, the site area and the ground conditions. Tell us about your project and we will propose an investigation programme and quotation.
Under the National Building Code 2024, soil testing is now expected before construction. We reply with a proposed programme and quotation.
Book a geotechnical survey in Kenya