Borehole Casing and Screen Installation: Technical Requirements and Best Practices

Technical guidance on borehole casing and well screens: materials, wall thickness, slot size, open area, placement opposite aquifers, centralisers and installation best practice.

By Quantum Geoconsultants hydrogeology teamUpdated 19 November 20262 min read
TopsoilLava flowFractured lava flowWater between lava flowsOlder lavas & tuffs Depth set by the survey

💧 Hydrogeology & Boreholes: a technical article by the Quantum Geoconsultants hydrogeology team.

Casing and screens form the permanent lining of a borehole. Poor choices here lead to collapsed holes, sand pumping, low yield and short borehole life. This article explains the requirements and best practice for borehole casing and well screen installation.

What casing and screens do

Casing materials

uPVC

The most common choice for water boreholes in Kenya. It does not corrode, is light and economical. It must have adequate wall thickness and pressure class for the depth, because collapse pressure increases with depth and during development.

Steel

Mild or galvanised steel is stronger and used for deep or large-diameter boreholes. It can corrode in saline or acidic water, shortening borehole life and causing iron problems.

Stainless steel

Durable and strong, with excellent screens, but costly. Used for high-value or corrosive settings.

Screen types

Slot size and open area

Slot size is chosen from the grain size of the aquifer and the gravel pack. Too wide and sand enters; too narrow and water entry is restricted and the screen clogs. Open area should be high enough that water enters at low velocity, which reduces head losses, sand movement and incrustation.

Placement

Screen placement comes from the drilling log, water strikes, airlift yields and geophysical logs. Best practice:

Diameter

Casing diameter must suit the pump to be installed, with clearance for cables and rising main. Common water borehole casings are 4 to 6 inches (about 100 to 150 mm) internal diameter, with larger sizes for high-yield production wells.

Installation best practice

  1. Check the hole is clean, to depth and straight enough.
  2. Lay out and measure all casing and screen lengths in order.
  3. Join sections with proper threaded or solvent joints, not improvised fixings.
  4. Fit centralisers at intervals so casing stays central for an even gravel pack.
  5. Lower carefully without forcing. If it sticks, pull back and clean the hole.
  6. Record the final as-built design: depths of screens, casing, sump and pack.

Common mistakes

How Quantum Geoconsultants can help

Our hydrogeologists design casing and screen strings from drilling logs, and supervise installation. See borehole drilling, borehole drilling procedures and borehole camera inspection to check existing casing.

Frequently asked questions

Should a borehole use uPVC or steel casing?

uPVC is corrosion-resistant and common for most water boreholes. Steel is stronger and used for very deep boreholes or where high loads are expected, but it can corrode in aggressive water.

How is screen slot size chosen?

Slot size is matched to the aquifer grain size and gravel pack so water enters freely while sand is held back.

Where should screens be placed?

Opposite the water-bearing zones identified from drilling logs, with plain casing opposite clays and dry or poor-quality zones.

💧 Water demand calculator

How much water does your borehole need to deliver each day? Enter your numbers for a quick planning estimate.

0litres per day
0suggested tank (litres)
0pump flow (m³/hour, solar)

Rough planning figures only, using typical daily use per person and per animal, with one day of storage and about 6 hours of good sun. Your test pumping result sets the final pump size.

Get a borehole quote for Kenya

Send us your location. We will advise on the survey, permits, expected depth and the full cost up to a working solar borehole.