You have paid for a site investigation and received a thick geotechnical report full of logs, tables and technical terms. It is tempting to skip to the bearing pressure and file the rest. That is a mistake. The report contains information that affects your foundation design, construction method, programme and cost. This guide explains how the report is organised and what to look for in each part.

Factual versus interpretive

Most reports follow BS 5930 and separate two kinds of information:

The factual part should be objective and complete. The interpretive part reflects the engineer’s judgement and applies to the specific project described. If your building changes significantly, the interpretation may need updating.

1. Introduction and scope

Check that the report describes your project correctly: building type, number of storeys, loads, basements and site area. If the engineer assumed a three-storey building and you are now building six, the recommendations may not apply.

2. Site description and geology

This section describes the site, its topography and drainage, and the published geology. It should mention anything unusual, such as fill, old structures, springs or signs of ground movement.

3. Fieldwork and location plan

A plan shows where each borehole, trial pit or test was carried out. Check that the points cover the building footprint. If all the boreholes are in one corner, ask why. Our article on how many boreholes an investigation needs explains typical spacing.

4. Borehole and trial pit logs

Logs are the core of the factual report. Each log shows depth on the left and, for each layer:

Tip: read the words, not just the numbers. “Very soft”, “loose”, “highly weathered” or “possible fill” are warnings.

5. Laboratory results

Tables and graphs show classification tests (moisture content, Atterberg limits, grading), strength tests, consolidation and swell tests, and chemical tests for concrete durability. Look for summary tables that relate results to depth and layer.

6. Ground model

A good interpretive report brings the data together into a simple ground model, often with a cross-section: “Topsoil 0.3 m over black cotton soil to 1.8 m, over stiff murram to 4.5 m, over weathered phonolite”. This is the most useful single summary for the design team.

7. Geotechnical parameters

The engineer gives design values for each layer, such as unit weight, strength, stiffness and permeability. These should be cautious, realistic values based on the test results, not simply the best or average result.

8. Foundation recommendations

Item What to check
Foundation type Strip, pad, raft or piles, and why
Founding stratum and depth Which layer, at what depth
Allowable bearing pressure The value, and the foundation size it applies to
Estimated settlement Total and differential, compared with what the structure can tolerate
Pile parameters Shaft and base resistance, pile type, testing
Floor slabs Ground-bearing or suspended, subgrade preparation

Our guide to bearing capacity from site investigation explains how the bearing value is derived.

9. Construction recommendations

Contractors should read this section closely. It covers:

10. Limitations

All reports include limitations. Ground conditions between boreholes are inferred, and conditions can differ. If you find something unexpected during construction, such as soft pockets, cavities or water, stop and call the geotechnical engineer.

Questions to ask the engineer

  1. Which result controls the bearing pressure?
  2. What are the main ground risks on this site?
  3. What should the contractor look out for during excavation?
  4. When should you be called to inspect the formation?

How Quantum Geoconsultants can help

Our reports separate facts from interpretation and give clear, practical recommendations. We are happy to explain them to your design team. See our geotechnical surveys in Kenya and Somalia.

Frequently asked questions

What is the difference between a factual and an interpretive geotechnical report?

A factual report records what was found: logs, test results and locations. An interpretive report uses those facts to build a ground model and give design parameters and recommendations.

What is allowable bearing pressure?

It is the pressure the ground can safely carry under a foundation, with an adequate margin against failure and acceptable settlement. It depends on the foundation size and depth as well as the soil.

Who should read the geotechnical report?

The structural engineer, architect, contractor and client should all read it. The contractor in particular needs the information on excavation, groundwater and difficult ground to plan the work and price it fairly.

🏗️ Request a geotechnical survey quote

The scope and cost of a geotechnical investigation depend on the size and type of structure, the site area and the ground conditions. Tell us about your project and we will propose an investigation programme and quotation.

Under the National Building Code 2024, soil testing is now expected before construction. We reply with a proposed programme and quotation.