A borehole can only be as good as its location. The same drilling effort can produce a high-yield borehole at one point and a dry hole a short distance away. Borehole siting is the process hydrogeologists use to choose the point with the best chance of success. This article explains how they make that decision.
Step 1: Understand the client’s needs
- Required daily volume and peak demand. See daily water demand.
- Water use: drinking, irrigation, livestock, industrial.
- Where water is needed, and where storage or towers will go.
- Budget and power options.
Step 2: Desk study
- Geological maps: rock types and structures.
- Existing boreholes: depths, yields, water levels and quality from records and neighbours.
- Topography and drainage: valleys, rivers and recharge areas.
- Satellite images: lineaments, vegetation and land use.
- Rainfall and recharge.
Step 3: Field reconnaissance
- Rock outcrops, fractures and dykes.
- Springs, wetlands and vegetation that indicates shallow water.
- Existing wells and boreholes.
- Contamination sources: latrines, septic tanks, livestock pens, fuel stores, dumps.
- Access for the drilling rig and space to work.
- Flooding risk at the site.
Step 4: Geophysical survey
Geophysics narrows down the options. Common methods:
- VES at candidate points to estimate depth and layers.
- 2D ERT to image fracture zones and weathering.
- EM profiling and magnetics to locate faults and dykes.
- TEM for deep aquifers.
The method depends on the geology. In basement rocks, finding fractures and deep weathering is the priority. In sedimentary basins, identifying fresh aquifers and avoiding clay and saline layers matters most.
Step 5: Interpretation and ranking
The hydrogeologist combines all the evidence and ranks candidate points. Factors include:
| Factor | Favourable |
|---|---|
| Geophysical response | Indicates thick aquifer, fractures or deep weathering |
| Geology | Known productive formation or structure |
| Nearby boreholes | Good yields and quality at similar depths |
| Topography | Valleys and lower slopes often better than ridges |
| Water quality risk | Low salinity, fluoride or iron risk |
| Contamination | Safe distance from latrines and other sources |
| Practicality | Rig access, space, distance to storage and users |
Step 6: Peg and report
- Peg the recommended point clearly on site and record coordinates.
- Peg an alternative point in case the first fails.
- Prepare a report with data, interpretation, recommended depth, expected yield range and risks. See our survey report checklist.
Contamination distances
A borehole should be well away from contamination sources and, where possible, upslope of them. The safe distance depends on soil and rock type: contaminants travel further in fractured rock and coarse sands than in clays. See safe distance from septic tanks and latrines.
Common siting mistakes
- Choosing a site for convenience, such as next to the house or gate.
- Moving the rig “a few metres” from the pegged point.
- Siting too close to latrines or septic tanks.
- Relying on a single geophysical point.
- Ignoring nearby borehole failures.
- Siting in a flood-prone hollow.
See why boreholes come up dry and water divining vs geophysical surveys.
How Quantum Geoconsultants can help
Our hydrogeologists combine geology, local data and geophysics to site boreholes across Kenya and Somalia. See our hydrogeological surveys in Kenya, Somalia and geophysical surveys.
Frequently asked questions
What is borehole siting?
The process of choosing the exact point to drill a water borehole, based on geology, hydrogeology, geophysical surveys, water quality risks, contamination sources and practical constraints.
How far should a borehole be from a pit latrine?
It depends on the geology and local guidelines. Many guidelines recommend tens of metres as a minimum, and more in fractured rock or sandy soils where contaminants travel easily. Check current local requirements.
Can I choose the borehole site myself?
You can suggest preferred areas for convenience, but the final point should be chosen by a hydrogeologist. A few metres can matter in fractured rock, and a convenient spot may be close to contamination.
💧 Water demand calculator
How much water does your borehole need to deliver each day? Enter your numbers for a quick planning estimate.
Rough planning figures only, using typical daily use per person and per animal, with one day of storage and about 6 hours of good sun. Your test pumping result sets the final pump size.