Foundation Settlement: Causes, Limits and Monitoring

Why foundations settle, the difference between total and differential settlement, typical tolerable limits, how settlement is predicted from site investigation and how it is monitored during and after construction.

By Quantum Geoconsultants geotechnical teamUpdated 20 November 20263 min read
Black cotton soil: swells & shrinksFirmer weathered layerRock Core box Know your ground before you build

🏗️ Geotechnical Engineering: a technical article by the Quantum Geoconsultants geotechnical team.

Every foundation settles. When a building is placed on the ground, the soil compresses under the added load. A few millimetres of uniform settlement is usually harmless. Large or uneven settlement is not: it cracks walls, jams doors, breaks pipes and can make buildings unsafe. This article explains the causes of foundation settlement, the limits engineers work to and how settlement is monitored.

Types of settlement

Type Description Typical soils
Immediate Occurs as load is applied, mostly elastic compression Sands, gravels, stiff soils
Consolidation Slow compression as water drains from clay Soft to firm clays and silts
Secondary (creep) Continues slowly after consolidation Soft, organic clays and peat

See the oedometer test for how consolidation settlement is predicted.

Causes of excessive settlement

Total and differential settlement

Total settlement is the downward movement of a point. Differential settlement is the difference between two points. A building that settles 40 mm uniformly may show little damage; one that settles 40 mm at one corner and 10 mm at another may crack badly.

Engineers also use angular distortion: differential settlement divided by the distance between points. Limits on angular distortion relate directly to cracking risk.

Typical tolerable limits

Limits depend on the structure type, materials and use. Published guidance, including Eurocode 7 informative values and classic research by Skempton, Burland and others, suggests approximate ranges such as:

Criterion Indicative value
Total settlement, isolated footings on clay Often limited to around 25 to 50 mm
Total settlement, rafts Larger values may be acceptable if uniform
Angular distortion, onset of cracking in framed buildings Around 1/500 is often used as a limit
Angular distortion, structural damage likely Around 1/150 to 1/300

These are general guides. Sensitive structures, such as tanks, machinery bases and buildings with brittle finishes, need tighter limits set by the structural engineer.

Predicting settlement

A geotechnical investigation provides the data:

The engineer calculates stress increases beneath each foundation and the resulting compression of each layer, then compares predicted settlements with the limits.

Reducing settlement

Monitoring settlement

  1. Install settlement points (studs or bolts) on columns, walls or foundations.
  2. Establish a stable benchmark outside the zone of influence.
  3. Take a baseline reading before significant loading.
  4. Level the points at regular intervals during and after construction using precise levelling.
  5. Plot settlement against time and load, and compare with predictions.

For larger projects, automatic sensors, tiltmeters and crack gauges add detail. See deformation monitoring surveys.

How Quantum Geoconsultants can help

We investigate ground conditions, predict settlement and provide monitoring surveys for buildings, tanks and embankments. See our geotechnical surveys in Kenya and our guide to cracks in walls.

Frequently asked questions

Is some foundation settlement normal?

Yes. Almost all foundations settle a little as the ground compresses under load. The concern is settlement that is large, uneven or continuing, because that causes cracking and damage.

What is differential settlement?

The difference in settlement between two parts of a structure. It distorts the building and causes cracks, so it is usually more damaging than uniform total settlement.

How is settlement monitored?

By precise levelling of fixed points on the structure at intervals, sometimes with automatic sensors, compared with a stable benchmark away from the building.

🏗️ Request a geotechnical survey quote

The scope and cost of a geotechnical investigation depend on the size and type of structure, the site area and the ground conditions. Tell us about your project and we will propose an investigation programme and quotation.

Under the National Building Code 2024, soil testing is now expected before construction. We reply with a proposed programme and quotation.