Ports, jetties, bridges across creeks, outfalls and coastal protection works all need ground information from under the water. Getting it means taking a drilling rig out over the sea, often in tides, swell and currents. Nearshore geotechnical drilling is a specialised activity in which the choice of platform matters as much as the drilling itself. This article explains the main options and how to choose between them.
Why the platform matters
Geotechnical drilling relies on a steady base. SPTs, sampling and coring all need the drill string to stay still relative to the seabed. If the platform rises and falls with waves or tide, the casing moves, samples are disturbed and depth records become unreliable. The platform must also be safe for the crew and stable under the weight of the rig, casing and samples.
Platform options
Jack-up platforms
A jack-up is a pontoon with legs that are lowered to the seabed and then used to raise the deck above wave height. Once jacked up, it does not move with waves or tide.
- Advantages: very stable, best data quality, works in moderate wave conditions.
- Limitations: limited by water depth and leg length; needs careful assessment of seabed bearing capacity under the legs; slower to move between locations.
Spud-leg pontoons
A modular pontoon held in place by spud legs pushed into the seabed. It resists horizontal movement but still floats, so it rises and falls with the tide.
- Advantages: quicker to assemble and move; suits sheltered, shallow water.
- Limitations: vertical movement must be managed with casing fixed to the seabed and regular depth checks.
Floating barges and vessels
A barge or vessel anchored on a multi-point mooring, with the rig drilling over the side or through a moon pool.
- Advantages: works in deeper water; mobile.
- Limitations: heave affects data quality; heave compensation or seabed frames are needed for good testing; depends on calm weather.
Temporary staging and land-based reach
Close to shore or in very shallow water, scaffold staging, causeways or a land-based rig on a temporary trestle may be the most practical solution, especially at low tide.
Comparison
| Platform | Water depth | Stability | Typical use |
|---|---|---|---|
| Jack-up | Shallow to moderate | Excellent | Ports, jetties, exposed coasts |
| Spud-leg pontoon | Shallow | Good horizontally, tidal movement | Sheltered harbours, rivers, creeks |
| Floating barge or vessel | Moderate to deep | Depends on sea state | Deeper water, calm conditions |
| Staging or causeway | Intertidal and very shallow | Good if well built | Shore approaches, outfalls |
Choosing a platform
Key factors are:
- Water depth including tide range at each borehole.
- Wave and swell climate and the season. Monsoon conditions along the Somali and Kenyan coasts limit working windows.
- Currents, which push on the platform and the casing.
- Seabed conditions: soft sediments may not support jack-up legs, while rock may prevent spud penetration.
- Rig weight and deck space for casing, tools, samples and crew.
- Access: launching sites, towing vessels and cranes.
- Number and spacing of boreholes, which affects how often the platform has to move.
Drilling procedure over water
- Position the platform using RTK GNSS and confirm the coordinates of the borehole.
- Measure water depth and record the time and tide level, so the seabed level can be reduced to the project datum. See hydrographic surveys.
- Install conductor casing from the deck into the seabed to guide the drill string and protect it from currents.
- Drill and sample, carrying out SPTs, undisturbed sampling and coring as specified.
- Record depths relative to the seabed and check them regularly against tide changes on floating platforms.
- Backfill the borehole if required and recover the casing.
Data quality challenges
- Soft seabed clays are easily disturbed; use thin-walled or piston samplers and minimise platform movement.
- Calcareous sands and coral limestone can give core loss; triple-tube coring improves recovery.
- Tidal movement can affect depth records on floating platforms unless carefully corrected.
- Samples must be protected from heat on deck and transported carefully. See logging marine boreholes.
Safety over water
Over-water drilling has extra hazards: drowning, man overboard, platform instability and severe weather. Essential controls include life jackets, a safety boat, weather monitoring and stop-work limits, secure handrails, emergency drills and a clear communication plan with shore. Jack-up leg penetration and pre-load must be checked before work begins.
How Quantum Geoconsultants can help
We plan and carry out nearshore investigations for ports and coastal structures, supported by bathymetric surveys. See our guide to port geotechnical investigations, our geotechnical surveys in Somalia and bathymetric surveys.
Frequently asked questions
What is a jack-up platform in geotechnical drilling?
A floating platform with legs that are lowered to the seabed and used to lift the deck clear of the water. It gives a stable, non-moving base for drilling, unlike a floating barge.
Can geotechnical boreholes be drilled from a floating barge?
Yes, in sheltered water with small waves, using heave compensation or a moon pool and casing to the seabed. In exposed sites, movement of a floating barge reduces sample and test quality.
How is the position of an over-water borehole fixed?
With RTK GNSS on the platform, checked against shore control points. Water depth is measured with an echo sounder or lead line and corrected to the project datum using tide readings.
🏗️ Request a geotechnical survey quote
The scope and cost of a geotechnical investigation depend on the size and type of structure, the site area and the ground conditions. Tell us about your project and we will propose an investigation programme and quotation.
Under the National Building Code 2024, soil testing is now expected before construction. We reply with a proposed programme and quotation.
Book a geotechnical survey in Kenya