Every building, road, bridge, water tower and dam rests on the ground, and the ground is the one construction material nobody chooses. A geotechnical site investigation finds out what that ground is made of, how strong it is, how much it will settle and how water moves through it, so engineers can design foundations that are safe and economical. This article explains what a site investigation involves, the standards behind it and why it should always come before construction.
What is a geotechnical site investigation?
A geotechnical site investigation (also called a ground investigation, soil investigation or soil test) is a planned programme of desk study, fieldwork and laboratory testing that describes the soil, rock and groundwater beneath a site. It answers the questions a structural or civil engineer needs answered before designing anything that loads the ground:
- What is under the site? The type, thickness and sequence of soil and rock layers.
- How strong is it? The bearing capacity and shear strength of each layer.
- How much will it move? Expected settlement, swelling or shrinkage under the new loads and with changing moisture.
- Where is the water? Groundwater levels and how they change with the seasons.
- Is the ground aggressive? Sulphates, chlorides and acidity that can attack concrete and steel.
- Are there hazards? Cavities, faults, soft or loose layers, fill, slopes that could fail, or swelling clays.
Why a site investigation matters before construction
Unexpected ground conditions are one of the most common causes of construction delays, cost overruns and structural damage. Cracked walls, sinking floor slabs, tilting buildings and failed retaining walls can very often be traced back to ground that was never properly investigated. A site investigation usually costs a small fraction of a project’s budget, yet it:
- Prevents failures by revealing weak, compressible or swelling ground before it is built on.
- Saves money by avoiding over-designed foundations that are deeper or heavier than the ground actually needs.
- Reduces construction risk, because contractors can price excavation, dewatering and piling accurately instead of adding large contingencies.
- Supports approvals. In Kenya, the National Building Code 2024 expects soil investigation before construction, and lenders, insurers and donors increasingly ask for a geotechnical report.
- Protects durability by identifying aggressive soils and groundwater so the right concrete mix and cover can be specified.
Common ground problems a site investigation reveals
East Africa has several ground conditions that regularly cause trouble when they are not investigated:
- Black cotton soil (expansive clay). These clays swell in the rains and shrink in the dry season, cracking walls, slabs and roads. They are widespread around Nairobi, Machakos, Kajiado and much of the Somali river valleys.
- Coral limestone with cavities. Along the Kenyan coast and in Mogadishu, limestone can be strong in one place and hollow a few metres away.
- Volcanic soils, ash and faults in the Rift Valley. Loose ash can erode or collapse, and ground fissures can open along faults.
- Soft alluvial clays and high groundwater near rivers and lakes, where settlement and low bearing capacity are a concern.
- Gypsum and saline soils in arid areas, which attack concrete and can dissolve over time.
The standards behind a site investigation
Professional site investigations follow recognised codes so that results are reliable and accepted by engineers, authorities and funders. The main ones used in Kenya and the region are:
- BS 5930, the British code of practice for ground investigations. It covers planning, desk study, fieldwork, sampling, logging and reporting.
- Eurocode 7 (BS EN 1997-1 and 1997-2), which links ground investigation to geotechnical design and gives guidance on the spacing and depth of investigation points.
- BS 1377 and the newer BS EN ISO 17892 series for laboratory soil testing.
- BS EN ISO 14688 and 14689 for identifying and classifying soil and rock.
- BS EN ISO 22476-3 for the Standard Penetration Test (SPT).
The stages of a geotechnical site investigation
1. Desk study
Before anyone goes to site, the engineer reviews geological maps, previous investigations nearby, satellite images, old land uses and the proposed structure. The desk study identifies likely ground conditions and hazards, and shapes the fieldwork plan.
2. Site walkover
A geotechnical engineer or engineering geologist walks the site to check access, look at exposures, cracks in nearby buildings, drainage, slopes and vegetation, and confirm where boreholes and trial pits can go. A topographic survey is often done at this stage so levels and positions are known.
3. Fieldwork
The main investigation combines several techniques:
- Boreholes drilled by rotary coring or percussion methods to recover soil and rock samples at depth.
- Standard Penetration Tests (SPT) at regular intervals in the boreholes, giving N-values that indicate soil density and strength.
- Rock coring, with core recovery and Rock Quality Designation (RQD) recorded to describe rock quality.
- Trial pits for shallow foundations, to see the soil profile directly and take bulk samples.
- Dynamic Cone Penetrometer (DCP) and plate load tests for roads, slabs and shallow footings.
- Groundwater observations and standpipe piezometers to record water levels over time.
- Geophysical surveys such as electrical resistivity and seismic refraction, which map the ground between boreholes and help detect cavities, faults and depth to rock.
4. Laboratory testing
Samples are tested to measure the properties used in design: moisture content, particle size distribution, Atterberg limits (plasticity), free swell and swell pressure for expansive clays, compaction and California Bearing Ratio (CBR) for roads, shear strength (triaxial or shear box), consolidation for settlement, and chemical tests for sulphates, chlorides and pH.
5. Reporting
The results are presented in two parts. The factual report contains borehole and trial pit logs, test results and site plans. The interpretive report (called the Ground Investigation Report under Eurocode 7) explains what the results mean: the ground model, design parameters, bearing capacity, expected settlement, recommended foundation type and depth, concrete protection and any construction risks.
How many boreholes, and how deep?
There is no single answer, because it depends on the structure, the loads and the variability of the ground. As a guide, Eurocode 7 Part 2 suggests investigation points at roughly 15 to 40 metres apart for high-rise and industrial buildings, and wider spacing for large open areas and roads. For pad and strip footings, investigation should usually extend to at least three times the footing width and not less than about 6 metres below the foundation, and deeper for rafts, piles and heavy structures. A small house on uniform ground may need only two or three boreholes or trial pits, while a high-rise or a dam needs a much more detailed programme.
What a site investigation costs and how long it takes
The cost depends on the number and depth of boreholes, the in-situ and laboratory tests needed, site access and distance. Fieldwork for a typical building plot takes a few days, laboratory testing one to three weeks, and the report follows soon after. Compared with the cost of repairing a cracked building or redesigning foundations during construction, a site investigation is one of the best-value steps in any project.
When should you commission a site investigation?
As early as possible: ideally once the site is chosen and the building’s size and layout are known, and before the structural design is finalised. Early investigation lets the design team choose the most economical foundation from the start. A second, more detailed phase can follow once the final layout is fixed.
How Quantum Geoconsultants can help
Quantum Geoconsultants carries out geotechnical site investigations to BS 5930 and Eurocode 7, from desk study and drilling to laboratory testing and clear design recommendations. We work across Kenya from our Nairobi base, and our personnel also have experience working in Somalia.
- Geotechnical surveys in Kenya
- Geotechnical surveys in Nairobi
- Geotechnical surveys in Somalia
- Geophysical surveys for construction
- Water tower construction, where foundation design depends on a site investigation
Planning a project? Send us your site location and building details and we will propose an investigation programme and quotation.
Frequently asked questions
What is a geotechnical site investigation?
It is a planned programme of desk study, fieldwork and laboratory testing that describes the soil, rock and groundwater beneath a site, so engineers can design safe and economical foundations.
Is a soil test required before construction in Kenya?
The National Building Code 2024 expects soil investigation before construction, and lenders, insurers and donors increasingly ask for a geotechnical report.
Which standards apply to site investigations?
The main ones are BS 5930 for ground investigation, Eurocode 7 (BS EN 1997) for geotechnical design, BS 1377 and BS EN ISO 17892 for laboratory tests, and BS EN ISO 14688 and 14689 for soil and rock classification.
How long does a site investigation take?
Fieldwork for a typical building plot takes a few days, laboratory testing one to three weeks, and the report follows soon after.
🏗️ Request a geotechnical survey quote
The scope and cost of a geotechnical investigation depend on the size and type of structure, the site area and the ground conditions. Tell us about your project and we will propose an investigation programme and quotation.
Under the National Building Code 2024, soil testing is now expected before construction. We reply with a proposed programme and quotation.