A borehole is a significant investment, and disagreements between clients and drillers are common. Most arise from contracts that are vague about what is included, how depth is measured or what happens if the borehole is dry. Before you sign, use this checklist to make sure your borehole drilling contract protects you and sets clear expectations for both sides.
1. Parties and site
- Full names and contacts of client and contractor.
- Site location with GPS coordinates and plot details.
- Reference to the hydrogeological survey report and the pegged drilling point. See our survey report checklist.
- Permit references and who is responsible for obtaining them.
2. Scope of work
List every activity clearly:
- Mobilisation and demobilisation.
- Drilling to a target depth, with a maximum depth or decision point.
- Casing, screens, gravel pack and sanitary seal.
- Development.
- Pumping test (type and duration).
- Water sampling and laboratory analysis.
- Headworks: casing height, cap, apron slab.
- Pump supply and installation, if included.
- Completion report.
3. Bill of quantities and rates
| Item | What to check |
|---|---|
| Drilling per metre | Rates by diameter and formation (soft, hard rock) |
| Casing and screens per metre | Material, diameter, class and brand |
| Gravel pack and grout | Quantity basis and material |
| Development and test pumping | Hourly or lump sum rates |
| Standby time | When it applies and the rate |
| Water for drilling | Who supplies it |
| Extras | Fishing for lost tools, extra casing, access works |
A per-metre contract is common, so total cost depends on final depth. Agree a maximum depth or a point at which the client is consulted before drilling further. See borehole timelines.
4. Materials specification
- Casing and screen type, diameter, pressure class and slot size. See casing and screens.
- Gravel pack grading and source. See gravel packing and sealing.
- Requirement for new, undamaged materials, with delivery inspection.
5. Dry and abandoned holes
This clause prevents many disputes. It should state:
- What is charged for a dry or low-yield borehole.
- Whether casing is installed or recovered.
- Whether and how a second site will be drilled, and at what rates.
- How abandoned holes are backfilled and sealed. See decommissioning.
- What happens if tools are lost in the hole.
See also why boreholes come up dry.
6. Supervision and records
- Who supervises: an independent hydrogeologist or the contractor’s own staff?
- Daily drilling records: depth, formation, penetration rate, water strikes.
- Right of the client or supervisor to inspect at any time.
- Decision points requiring client approval (final depth, casing design).
7. Testing and water quality
- Development until water is clear and sand-free.
- Step-drawdown and constant rate test durations. See pumping tests.
- Water sample taken by whom and tested at which accredited laboratory.
8. Payment terms
Link payments to milestones, for example:
- Mobilisation.
- Completion of drilling.
- Completion of construction and development.
- Pumping test and water analysis.
- Handover of completion report, with a retention held until then.
9. Timeline and delays
- Start date and expected duration.
- Responsibilities for access, water and security.
- Treatment of delays caused by weather, breakdowns or site conditions.
10. Warranty and liability
- Warranty on workmanship and materials, for example against casing failure.
- Pump warranty if supplied.
- Insurance and responsibility for damage to property.
- Health and safety responsibilities on site.
11. Handover documents
Insist on a full completion report: drilling log, construction diagram, development record, pumping test data and analysis, water quality certificate and pump recommendation. See understanding your completion report.
How Quantum Geoconsultants can help
We provide transparent contracts with clear bills of quantities, dry hole terms and full completion reports, and we supervise drilling for clients using other contractors. See our borehole drilling in Kenya and Somalia.
Frequently asked questions
What should a borehole drilling contract include?
A clear scope, bill of quantities with unit rates, material specifications, depth and diameter, development and pumping test requirements, water quality testing, dry hole terms, payment schedule, timeline, warranty and handover documents.
Who pays if the borehole is dry?
That depends on the contract. Usually the client pays for drilling done, but the contract should state exactly what is charged for a dry or abandoned hole and what happens next.
Should I pay the full amount upfront?
It is safer to pay in stages linked to milestones, such as mobilisation, drilling, construction, testing and handover, with a retention held until documents are delivered.
💧 Water demand calculator
How much water does your borehole need to deliver each day? Enter your numbers for a quick planning estimate.
Rough planning figures only, using typical daily use per person and per animal, with one day of storage and about 6 hours of good sun. Your test pumping result sets the final pump size.
Send these numbers on WhatsAppGet a borehole quote for Kenya
Send us your location. We will advise on the survey, permits, expected depth and the full cost up to a working solar borehole.