On a coastal project, levels come from two worlds. Land surveyors work to a height datum based on mean sea level. Marine surveyors and navigators work to chart datum, a low-water reference. If the relationship between them is wrong, quay walls are built at the wrong height, dredging goes too deep or not deep enough and drainage outfalls flood. This article explains tidal datums and how to manage them on marine projects.
Tides in brief
Tides are caused mainly by the gravitational pull of the moon and sun. Water levels rise and fall typically twice a day along most East African and Somali coasts, with larger spring tides around new and full moon and smaller neap tides in between. Tidal range varies along the coast. Weather, swell and river flow add further variation.
Common tidal levels
| Abbreviation | Name | Meaning |
|---|---|---|
| HAT | Highest Astronomical Tide | Highest predicted tide under average weather |
| MHWS | Mean High Water Springs | Average high water at spring tides |
| MHWN | Mean High Water Neaps | Average high water at neap tides |
| MSL | Mean Sea Level | Average sea level over a long period |
| MLWN | Mean Low Water Neaps | Average low water at neap tides |
| MLWS | Mean Low Water Springs | Average low water at spring tides |
| LAT | Lowest Astronomical Tide | Lowest predicted tide under average weather |
Chart datum
Chart datum (CD) is chosen so that the tide rarely falls below it. In many places it is set at or close to LAT. Depths on charts and in dredging specifications are given below CD. A “–12 m CD” berth means the seabed is 12 m below chart datum, and the actual water depth at any moment is that plus the tide height above CD.
Land datum
National land levelling networks are based on a mean sea level determined at one or more tide gauges. Benchmarks are given heights above this datum. GNSS heights must be converted using a geoid model or local calibration. See levelling surveys and coordinate systems.
Linking chart datum and land datum
For a project, the key value is the offset between chart datum and the land datum at the site. It is established by:
- Installing a tide gauge at or near the site.
- Recording water levels over a period, ideally at least a month to capture spring and neap cycles, and longer for better accuracy.
- Levelling or GNSS connection from the gauge zero to land benchmarks.
- Tidal analysis, comparing with a long-term reference station where available, to estimate MSL, LAT and other levels.
On remote coasts where official tidal data are limited, the project may need to establish its own datum and document it carefully.
Tides in marine surveys
Bathymetry
Echo sounders measure depth below the transducer. To give seabed levels, soundings are reduced using the water level at the time of each sounding, from a tide gauge or RTK GNSS heights. See bathymetric surveys.
Geotechnical boreholes over water
Seabed levels at each borehole must be reduced to the project datum using the tide at the time of measurement. See logging marine boreholes.
Coastal and shoreline surveys
Beach profiles and shoreline positions are usually referenced to a tidal level such as MHWS or MSL. See coastal erosion in Somalia.
Design uses
- Quay deck levels relative to high water and wave run-up.
- Dredged depths relative to CD for design vessels.
- Breakwater crest levels.
- Outfall and intake levels.
- Flood levels for coastal buildings and roads.
- Allowance for sea level rise over the design life.
Common mistakes
| Mistake | Consequence |
|---|---|
| Mixing CD depths and land levels without conversion | Errors equal to the datum offset, often a metre or more |
| Short tide records | Inaccurate LAT and MSL estimates |
| Tide gauge not tied to land benchmarks | No reliable link between marine and land surveys |
| Wrong sign convention (depths positive vs levels negative) | Inverted surfaces and wrong volumes |
| Undocumented datum | Confusion between consultants and contractors |
How Quantum Geoconsultants can help
We establish tide gauges, tie them to land control and deliver bathymetric and topographic data on a consistent datum. See our bathymetric surveys in Somalia and our guide to hydrographic surveys.
Frequently asked questions
What is chart datum?
The reference level used for depths on nautical charts, usually set at or near the lowest astronomical tide so that the water is rarely shallower than charted. Depths are measured below it; drying heights above it.
Why do land and sea levels use different datums?
Land surveys usually refer to a national height datum based on mean sea level, while charts use a low-water datum for navigation safety. Projects that cross the shoreline must relate the two.
How is a tidal datum established?
By recording water levels with a tide gauge over a period, ideally long enough to capture tidal cycles, analysing the tides and connecting the gauge to land benchmarks by levelling or GNSS.
📐 Request a topographic survey quote
The cost of a topographic survey depends mainly on the size of the site, the level of detail needed, the ground cover and whether a drone can be used. Tell us about your site and we will recommend a method and send a quotation.
We reply with the recommended method, deliverables and a quotation. Prices are not listed online because every site is different.
Get a topographic survey quote
Send us your site location, its approximate size and what the survey is for. We will recommend ground or drone methods and send a quotation, including mobilisation from our Nairobi base.